It’s projected to cost ComEd $3.1B to connect data centers to the grid
Six of the data centers will need over $100 million in infrastructure costs to connect to the grid.
Six of the data centers will need over $100 million in infrastructure costs to connect to the grid.
Report includes policy recommendations that were part of the POWER Act.
If approved, the amended request would add around $7-8 to monthly bills, rather than the $10-11 originally sought.
The hikes would amount to about $300 a year combined by 2028.