• About Us
  • Contact Us
  • Privacy Policy
Wednesday, July 8, 2026
No Result
View All Result
CNI
Subscribe
  • Home
  • News
    • Business
      • Economy
      • Technology
    • Capitol Briefs
    • Courts
      • Law Enforcement
    • Corruption Cases
      • Madigan Trial
        • Michael Madigan: The Rise and Fall
        • Madigan Trial in Review
      • ComEd 4 Trial
      • Emil Jones Trial
      • Paul La Schiazza Trial
      • Sam McCann Trial
      • Tim Mapes Trial
      • James Weiss Trial
    • Education
    • Environment
      • Agriculture
      • Energy
    • Government
      • Budget
      • Health
      • Immigration
      • Infrastructure
    • Healing Illinois
  • Investigations
    • Police Hiring
    • No Schoolers
    • Funeral Home
    • Culture of Cruelty
  • Elections
    • Election Guide
    • Candidates Questionnaire
    • Primary Results
  • CNI InsiderNew
  • Podcasts
  • About Us
    • News Team
    • Events
    • Careers
    • Privacy
    • Terms
  • Media Center
    • Pressroom
    • Republish Guidelines
    • Press Releases
    • Editorial Independence
    • Conflicts of Interest
    • Code of Ethics
    • Submit News Tip
    • Contact
  • Support Us
    • Support
    • Donors
CNI

Cairo port project gets additional funding, but construction timeline still uncertain

Long-delayed project moving forward under new leadership

Peter HancockbyPeter Hancock
August 26, 2023
in Economy
A A
Barges

Barges are pictured on the Ohio River near Cairo. (Capitol News Illinois photo by Peter Hancock)

4.3k
VIEWS
FacebookShareReddit

SPRINGFIELD – Both the state and federal governments are pumping additional money into plans to develop a riverport in southern Illinois at the confluence of the Ohio and Mississippi Rivers.

President Joe Biden’s administration announced Wednesday that the Alexander-Cairo Port District will receive a $150,000 grant to develop a master plan to identify the scope for port development and the future of the riverport.

And the Illinois Department of Transportation recently authorized an additional $790,000 for planning and development.

The new federal money will come from the Delta Regional Authority, an agency established in 2000 to promote and encourage economic development of the lower Mississippi River and Alabama Black Belt regions. The funding is part of the Bipartisan Infrastructure Law that President Biden signed in 2021.

The state money is part of a $40 million investment that was originally appropriated in the 2019 Rebuild Illinois capital improvements program.

That would cover only a fraction of the overall cost of development, which the Illinois Answers Project reported in March could be as high as $250 to $300 million. But officials have said they hope to receive private investment to cover most of the costs once they secure the necessary state and federal permits.

Officials had originally hoped to start construction on the project in 2022 and to have it operational in 2024. But the project stalled amid disagreements between IDOT and port district officials over how the state funds appropriated so far have been spent.

According to Comptroller Susana Mendoza’s office, the state has spent just over $3 million on the project since fiscal year 2019.

allwyn allwyn allwyn
ADVERTISEMENT

IDOT announced in October last year that it was releasing another $3.4 million for the project, but  Mendoza’s office said this week that none of that money has gone out.

At that time, the port district had requested nearly $7.5 million in reimbursements. But IDOT Secretary Omer Osman wrote in a letter to the district’s board chairman at the time, Larry Klein, that IDOT could not approve just over $4 million in requested money, either because the costs identified were not eligible for reimbursement with bond funds or the district had not provided sufficient information to process the request.

Osman also said in that letter that the administration had become deeply concerned that more than half of the funds spent by the state up to that point had been used for “consulting, project and grant management, and development expertise services.”

“In the future, state funds should be used for the engineering, site readiness, and environmental work necessary to complete the development of the port terminal,” he wrote. “Minimal funds may be used for consultation services.”

In February, the industry publication Waterways Journal reported that the project had stalled after a number of contracts had expired and no funding had been received since June 2022.

Now, however, the board has a new chairman, Alexander County State’s Attorney Zach Gowin, who took over as chairman in March. Klein remains on the board as vice chairman.

Gowin said in an interview Wednesday that the reason none of the $3.4 million announced in October had been spent yet was because the board had not yet submitted any vouchers for reimbursement. But he said the board hopes to begin the first of what could be several environmental studies by the end of the year. He declined to estimate when construction might begin.

“I don’t like putting a lot of timelines out there for people because I like to under-promise and over-deliver myself,” he said.

He said the environmental studies are needed to support applications for the numerous federal permits the project will need before construction begins.

“We’re happy that we’re making forward progress right now,” Gowin said. “I think all of us, including the board, would like to have a fast-forward button. But we’re building a port from the ground up, which is a great benefit, a great blessing to us because we can build it in a way that is responsive to the needs of the market and we don’t have to retrofit anything.”

Gov. JB Pritzker said Friday that he understands the project will take longer than he’d hoped it would.

“The Cairo port project is something that requires a lot of federal approvals,” he said at an unrelated appearance in Carterville. “It requires the local organization to make sure that they have all their plans in place. And we’ve got to make sure that the businesses are lined up and understand what the timing will be. But to match all that up takes a few years, and that’s the process that we’re in now.”


Documents to download

  • Cairo letter (1)

Capitol News Illinois is a nonprofit, nonpartisan news service covering state government. It is distributed to hundreds of print and broadcast outlets statewide. It is funded primarily by the Illinois Press Foundation and the Robert R. McCormick Foundation, along with major contributions from the Illinois Broadcasters Foundation and Southern Illinois Editorial Association.

Tags: CairoCairo port projecteconomy
Peter Hancock

Peter Hancock

Peter was one of the founding reporters with Capitol News Illinois. He came to Springfield after many years working in Topeka, Kansas, where he covered the Kansas statehouse and other beats. He began his reporting career in 1989 at a small county weekly newspaper and has worked in a variety of settings including both daily and nondaily newspapers, online media and public radio. A native of the Kansas City area, he has degrees in political science and education from the University of Kansas.

Related Posts

Illinois’ ‘swipe fee’ law on the brink after another delay, adverse court ruling

Illinois’ ‘swipe fee’ law on the brink after another delay, adverse court ruling

June 2, 2026
4.8k
Trucks

20,000 trucks a day: Life near a booming warehouse hub

May 16, 2026
1.1k

Creative Commons License

Republish our articles for free, online or in print, under a Creative Commons license.

Republish this article

Creative Commons Attribution-NoDerivatives 4.0 International License

This work is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

When republishing or co-publishing our stories, please copy and paste our tracking code (found at the bottom of the copy below - it includes the words "republication-tracker-tool") anywhere in the body of this article in your website’s content management system. This will let us know how much traffic our story has received. Republishing Guidelines.

Cairo port project gets additional funding, but construction timeline still uncertain

by Peter Hancock, Capitol News Illinois
August 26, 2023

1
Facebook Twitter Bluesky Soundcloud Instagram Youtube RSS
CNI
2501 Chatham Road, Suite 200
Springfield, IL 62704
editors@capitolnewsillinois.com
 
  • About Us
  • Contact Us
  • Media Center
  • Privacy Policy
  • Terms of Use

Capitol News Illinois is a nonprofit, nonpartisan news service covering state government. A service of the Illinois Press Foundation.

SubscribeMore news from the Illinois Statehouse delivered to your inbox.

© 2026 Capitol News Illinois

No Result
View All Result
  • Home
  • News
    • Business
      • Economy
      • Technology
    • Capitol Briefs
    • Courts
      • Corruption Cases
      • Law Enforcement
    • Environment
      • Agriculture
      • Energy
    • Government
      • Budget
      • Education
      • Health
      • Immigration
      • Infrastructure
    • Healing Illinois
  • Investigations
    • Police Hiring
    • No Schoolers
    • Funeral Home
    • Culture of Cruelty
  • Elections
    • Election Guide
    • Candidates Questionnaire
    • Primary Results
  • Capitol News Insider
  • Podcasts
  • About
  • Media
  • Support
  • Subscribe

© 2026 Capitol News Illinois